Morrison Knudsen selected Padgett, Inc. for an on-going job, consisting of the removal of 400 machines used at the old Naval Ordinance facility for the manufacture of gun barrels. Before each machine could be moved, it had to first be drained and decontaminated of oil and chemicals. It was then coated with Cosmoline* and wrapped in black plastic to await being transferred to other buildings on site, scrapped, or loaded onto trucks for shipment.
Padgett became responsible for the removal of 28 machines of various sizes, shapes, and weights. Some of the machines were massive. One particular machine, originally installed on July 4, 1942, consisted of 7 pieces, weighing from 19 tons to 64 tons each. This machine was dismantled and loaded onto 16 semi-trailers for transportation.
Each machine was located over a pit that had to be cleaned and mapped, (to insure that any cracks were documented). A typical pit was 30 ft. wide x 60 ft. long x 6 ft. deep. After a pit was cleaned and mapped, it was backfilled with gravel to 15 inches below existing floor level, and then filled with rebar and concrete to bring the pit level with the existing floor.
This particular project required the total expertise of Padgett's rigging experience. Two overhead cranes were linked together to accomplish the 60-70 ton lifts. A 1200-36 Gantry System with special rigging, and 2 large forklifts were used to remove the machinery from the pit areas. Pieces taken from the pit areas were placed onto a 200-ton die cart, (designed and built by Padgett), for removal from the building. Once outside, a 90-ton truck crane was used to transfer the machinery to a semi-trailer.
Under the guidance of Project Estimator Steve Reardon, and Field Superintendent Darrel Herron, this project was finished safely and on schedule.